Minister of Petroleum and Mineral Resources Karim Badawi announced on Thursday the start of production from the West Mina gas field in the Mediterranean, two months ahead of schedule, as part of efforts to accelerate the development of new discoveries and boost domestic gas output.
The project has brought two wells into production with a combined output of 160 million cubic feet of natural gas per day and approximately 3,000 barrels of condensates per day. The first well, West Mina-2, began production at a rate of 60 million cubic feet per day, while West Mina-1 entered production at 100 million cubic feet per day.
The development is being implemented through a partnership between the Egyptian Natural Gas Holding Company (EGAS), Shell and KUFPEC.
Badawi said the project reflects the positive impact of renewed investment in Egypt’s oil and gas sector and the restoration of investor confidence following the settlement of outstanding dues owed to foreign partners in June 2026. He noted that improved investment conditions have helped accelerate exploration, field development and the addition of new wells to the production map.
The minister added that increasing exploration and production remains a central pillar of the ministry’s strategy to strengthen domestic energy supplies and meet growing market demand.
According to sector estimates, the West Mina field contains around 245 billion cubic feet of recoverable natural gas reserves and approximately 5 million barrels of condensates, underlining the project’s economic significance and contribution to Egypt’s energy sector.