• Advertise
  • Privacy & Policy
  • Contact
Friday, December 5, 2025
itida
Egyptian Gazette

Editor-in-Chief

Mohamed Fahmy

Board Chairman

Tarek Lotfy

  • HOME
  • EGYPT
    • Local
    • Features
  • World
    • National Day
  • Technology
  • BUSINESS
    • Real Estate
    • Automotive
  • SPORTS
  • ENTERTAINMENT
    • Arts
    • Health
    • Lifestyle
    • Travel
  • Skyward
    • Snippets from EgyptAir history
  • MORE
    • Multimedia
      • Video
      • Podcast
      • Gallery
    • OP-ED
No Result
View All Result
  • HOME
  • EGYPT
    • Local
    • Features
  • World
    • National Day
  • Technology
  • BUSINESS
    • Real Estate
    • Automotive
  • SPORTS
  • ENTERTAINMENT
    • Arts
    • Health
    • Lifestyle
    • Travel
  • Skyward
    • Snippets from EgyptAir history
  • MORE
    • Multimedia
      • Video
      • Podcast
      • Gallery
    • OP-ED
No Result
View All Result
Egyptian Gazette
Home Business Real Estate

MG Developments finishes most of its projects, plans to launch new one in 2022

by Hamed Mahmoud
March 14, 2022
in Real Estate
MG Developments finishes most of its projects, plans to launch new one in 2022 1 - Egyptian Gazette
Share on FacebookWhatsapp

MG Developments announces its success during 2021 as its achievements reach 100% by exceeding the timetable for implementation rates to maintain its leadership in the real estate market.

Mohamed Metawee, chairman of MG Developments, says that the group was able to achieve completion rates that reach 100% in the various sectors.

“We were able to complete 100% of the Indego, Cyan and the “Royal Villas” phase in the Blue Blue project, Ain Sokhna, and we reach 90% of the “Azure” phase, and we are able to complete 75% of the “Navy” phase 24 months ahead of schedule, in addition to completing 100% of “Marka Mall”, he adds.

Moreover, he indicates that concerning the administrative HQ project on 90th Street in the 5th Settlement, 93% of the volume of business has been reached and it is scheduled to be completed during the summer of 2022. The land area that the project is built is 5000 sqm, with an investment value of LE1b. The management and operation work has been assigned to Savills.

He states that the excavation and concrete works have been completed in the Premium Business project, which is the 2nd commercial administrative project in the 5th Settlement, with an initial investment of LE200m.

Also, he confirms that regarding the group’s projects in the NAC, 82% of the commercial administrative ProMark project has been completed, with investments of EGP 1.2 bn. The construction work of The Mark project will start during March 2022, as the company uses a large group of contracting companies to implement the works.

Furthermore, seeking to establish an alliance with some companies to establish a new project in the NAC, which will be announced soon.

Tags: Blue BlueMG DevelopmentsNACnavyThe Mark

Discussion about this post

ADVERTISEMENT
egyptian-gazette-logo

The Egyptian Gazette is the oldest English-language daily newspaper in the Middle East.
It was first published on January 26, 1880 and it is part of El Tahrir Printing and Publishing House.

Follow Us

Gazette Notifications

Would you like to receive notifications on our latest news ?

  • Advertise
  • Privacy & Policy
  • Contact

Copyrights for © Egyptian Gazette - Administered by Digital Transformation Management.

No Result
View All Result
  • HOME
  • EGYPT
    • Local
    • Features
  • World
    • National Day
  • Technology
  • BUSINESS
    • Real Estate
    • Automotive
  • SPORTS
  • ENTERTAINMENT
    • Arts
    • Health
    • Lifestyle
    • Travel
  • Skyward
    • Snippets from EgyptAir history
  • MORE
    • Multimedia
      • Video
      • Podcast
      • Gallery
    • OP-ED

Copyrights for © Egyptian Gazette - Administered by Digital Transformation Management.

This website uses cookies. By continuing to use this website you are giving consent to cookies being used. Visit our Privacy and Cookie Policy.